Wednesday, 8 January 2014

Irony, Irony, Such Bitter Irony

Documents, it seems, are a little like London Buses.  You don't see one for a while, then a group of them come barrelling along all at once.

Having drawn attention to what appears to be a cynical attempt to divide and conquer public opinion to the A344 closure by Wiltshire County Council staff in 2005 (before it became the Wiltshire Council unitary authority) and the about face on the this issue by Wiltshire Councillors in 2011, another interesting document has crawled out of the woodwork.

What has emerged is a single page of the A303 Trunk Road (Stonehenge Improvement) Report, prepared for the First Secretary of State and the Secretary of State for Transport by Mr M Ellison.  Specifically, and, by design, a poor attempt at humour, or simply coincidence; but certainly by the bitterest of ironies - page 344.

Yes, you read that correctly, page 344


It is worth reading - as ever, click on the image to enlarge it.  Read it - again and again. Back in 2005, the Highways Agency had it right and the then Wiltshire County Council made its stance quite clear.

If any of you are left under any illusion that governments make decisions based on the available evidence, or on expert advice, then let this shatter it - once and for all.  The Inspector's conclusion is a stark prophecy of what would happen:

I conclude that the closure of the A344 independently of the proposed improvement of the A303 would not be justifiable, in that it would increase congestion on the A303 and elsewhere in the local road system, causing additional problems for emergency vehicles.

Well, I guess you would have to ask yourselves which half-wits were the recipients of this report in 2005.  Well, unless memory fails, I guess this would be none other than John "Two-Jags" Prescott and Alistair "Flipper" Darling.  Need I write more?

Wednesday, 4 December 2013

A Helpful Meeting with the National Trust

Last night, representatives of STAG met with two representatives of the National Trust, in Shrewton. The National Trust have owned a lot of the land around and about Stonehenge, in what now forms the Stonehenge World Heritage site, since 1927 and clearly have an interest in what happens to the area in the future - including the impact any improvement to the A303 might have on land in their custodianship.



A meeting of this sort, between a protest group and a public body - albeit a charitable one, could have been a recipe for acrimony and backward-looking hostility.  As it was, both sides agreed at the outset that regardless of any historical concerns, we all needed to focus on the future - and that was the spirit in which we engaged.  Although we didn't make any specific agreements, for that wasn't really the intention of the meeting, it did seem that there would be a lot of common ground as we move forward to attempt to find a solution to the seemingly intractable problem of the A303. The sort of thing I mean is a desire to minimise any impact on virgin countryside - including National Trust land, the World Heritage site and privately owned land.  A desire to minimise the impact on local communities of any improvements to the A303 and a recognition that closure of the A344 had led to the predicted rat-running along the Packway in Larkhill to Shrewton and in other more far-flung communities.

We were particularly taken with the fact that the two National Trust representatives had taken the time to drive into Shrewton along part of the rat-run and had noted the narrowness of the road, the lack of pavements, the bends and the proximity of the school.  They were also very pro-active in suggesting and discussing the sorts of improvements to sign-age and road structure that could improve the situation.  These might only be short-term fixes, but ones that could easily prevent a fatality or serious injury until such time as the A303 is dualled - SH2 a reality. 

Looking forward to the forthcoming feasibility study, it seems that the National Trust are willing to look at any and all options for routing the A303 past Stonehenge - to the north of the current route, to the south of it, or under it - recognising that tunnelling through unfavourable rock strata has improved enormously in the last 5 years. 

I don't think either STAG or the NT were in favour of a conventional dual-carriageway along the current route of the A303 between Stonehenge Bottom and Longbarrow Roundabout - not least because of the problem caused by rubber-necking car drives taken photos of Stonehenge as they pass by; bad enough now in near stationary traffic, but a recipe for carnage if traffic speeds do increase again - it seems that getting the travelling public to move off their main route by 500m (the old visitor's centre) was acceptable, but asking them to go 1 to 2km off their route is too much!

So, these are clearly folks we can work with in the future - and look forward to doing so.  Let's hope that some of the other stakeholders are prepared to be as forthcoming and open-minded.  What is certain is that after all the reviews and public inquiries that have already taken place, there will be no perfect solution, acceptable to all and that can be constructed in an instant at minimal cost and disturbance.  Compromises will have to be made - and likely by all parties. 


Time will tell if the meeting in London today between the Minister and representatives of Wiltshire, Somerset and Devon Councillors will be entered into in the same spirit.

Sunday, 27 October 2013

Spend Any Money Saved On HS2 on SH2: Dual the A303, the A358 and the A30

The Sunday papers are filled with stories of Labour plans to axe the £42 billion HS2 high-speed rail link from London to the North of England in favour of a £6 billion route along the line of the former Great Central Railway closed by Dr Beeching in the mid 1960s.  Basically, savings can be made by adopting a route that is still largely undeveloped - affecting far fewer people than the proposed route for the HS2 and requiring less unspoilt countryside to be sacrificed. OK, the size of Labour's predicted saving may be an over-estimate, but money could be saved and the North could get a viable high speed link.



Rumours abound that many Tory and Lib-Dem politicians are also hoping to bail out of the HS2 project, but want to spend any money that is saved on sorting out other transport infrastructure problems in the UK.  What could be better than sorting out the main route westward from London - the entire length of the A303, the A358 and the A30?  The most sensible way of doing this would be in overcoming the long-standing sticking point that is the Stonehenge World Heritage Site.   What we need is SH2, not H2S.

So, there you have it, a possible way to achieve 2 major transport infrastructure goals, allow politicians of all flavours to backtrack on the original HS2 plans without any loss of face, and fund SH2, including a dual carriageway bypass for us here in Winterbourne Stoke, with a few bob left over for some other projects.



SH2
The real engine for growth!

Tuesday, 22 October 2013

When Is a Road Not a (Rural) Road?

When is a road not a rural road?  Quite simply, when the Highways Agency (HA) have anything to do with it and it suits them.

We mentioned in a previous post that we'd put in a Freedom of Information Act request using the What do They Know website to ask the Highways Agency a fairly simple question - how wide was the A303 as it passed through our village of Winterbourne Stoke.



The reason we asked the question was that at certain points within the village, the A303 looks and feels much narrower than on other parts of the single-carriageway stretches of the road between Beacon Hill and Honiton.   We suspected the reason for the narrowness of the A303 in Winterbourne Stoke was the bridge over the River Till, a Grade II listed structure, built in 1939 and pre-dating the creation of the A303 trunk road in 1958.

We'd already made a few measurements of the road ourselves - on the premise of never ask an FOIA unless you already have, or strongly suspect you have, the answer.  So whilst we hoped we might get some genuine data, we half-expected we might get a less than satisfactory response - and so it turned out.


Click on the picture to see an enlarged view.  Basically, the HA claimed that the A303 is shown in their HAPMS database to be 7.3 metres wide at 20 sites on a 1 mile stretch of the A303 as it runs through the village.  This, according to our own measurements, was clearly complete and utter nonsense and it looked as if the HA had simply recorded the minimum desirable width of a an A road as the actual width of the A303.  An honest mistake, dodgy instrumentation, incompetence or worse?  Well that is for others to establish, but we couldn't let it rest and went back to the HA for further clarification and to point out what we thought was a problem with the data. 

The reason that this is so important is that public inquiries, reviews and other studies, rely on the HA to produce accurate data on roads to enable those inquiries to come to informed decisions as to how poor roads might be and how essential it might be to upgrade them.  Given incorrect data, they might be led to the wrong decisions.  This might have already happened in the past and might happen again in the forthcoming review of the A303.

Yesterday, we received a follow-up answer from the HA and I had to confess that my jaw hit the floor when I saw, shortly before I burst into bouts of uncontrollable laughter.  Strangely, others who saw the letter had a similar reaction, making comments such as:

"What (expletive deleted) planet are they on?"

"Does the HA provide LSD for its staff?"

"Have they ever been on the A303?"

What could possibly have provoked such a reaction?



Well, how about the HA statement that the "A303 through Winterbourne Stoke is most suitably referred to as an Urban setting".  

I am not quite sure how the HA 'expert' arrived at this conclusion, nor does he explain, but we would have thought that the definition of urban is very clear - it relates to a town or city - not a small village with under 80 dwellings set in a rural parish, in a rural ward of a rural county. 

However, to make life very straightforward for the HA and to avoid any possible confusion, we have pointed out that there is an HMG definition of rural and urban.  Both the HA and the Department for Transport use this definition in their publications - so you might expect that it would be used in defining whether a road is urban or rural.  The UK government define "urban" as outlined below:

"As a standard for general purposes a threshold population of 10,000 is recommended, with
all settlements of over 10,000 treated as urban areas and smaller settlements, together
with all other land, treated as rural".


So, a road in an urban setting would be one that ran through a population centre with a population of 10,000 or more.   Hmm, Winterbourne Stoke has just over 200 - hardly an urban setting then.  Unless, of course, the HA are counting the people stuck in traffic jams in Winterbourne Stoke as being part of the permanent resident population - well I suppose it does sometimes feel a bit like that.

We've gone back to the HA to ask them to try again and to point out to their expert the difference between rural and urban settings.   We've also asked them to clarify where, in their alternate reality, to the east and west of Winterbourne Stoke, does the urban setting of the A303 turn into a rural setting.

This set us thinking a bit.  If HA are right and we really are an urban setting, then it is government policy to have speeds of no more than 30 mph through the village because of the houses alongside the road. They would prefer the speed limit should be reduced to 20mph because of the number of properties with entrances onto the A303 in the village (>20- try counting, you'll probably have more than enough time)  - along with suitable traffic calming measures - road humps, chicanes, planters, etc.  So HA - if you are correct, remove the 40mph sign and lower the speed limit to meet government policy recommendations.  Whilst you may not be able to enforce the speed limit, the traffic calming measures would ensure a 24/7 traffic jam that would achieve the effect for you.

Of course, if Winterbourne Stoke is a rural setting, as we strongly suspect it might be, then the A303 is structurally too narrow to be a rural, all-purpose, mainline road road and that gives the HA a bit of a head-ache.  What are they going to do?   By rights, you'd think they should de-trunk the road. 

What is abundantly clear is that the HA can't be allowed have it both ways - and perhaps they should draw the attention of Ministers to their past mistakes to avoid repetition in the coming months.

Finally, you'll note in the HA's second response that the author accepts our road measurement without question.  Not only does the author accept it, he re-states it as a matter of fact.  A suspicious person might conclude, on the basis of this, that the HA's first answer to us was intended to deceive.  Now why might that be?


Saturday, 12 October 2013

John Glen MP

Yesterday evening I had a very interesting e-mail exchange with John Glen MP regarding his views of the traffic issues in the villages around Stonehenge following the closure of the A344, the changes to the Airman's Cross junction and the "improvements" to the Longbarrow roundabout, as well as the more general issue of the need to dual the A303 along its entire length.

I wanted to elicit John's views for two reasons.  First, I had sensed a perception, rightly or wrongly, in some quarters that, in relation to the A303, John was not being as supportive to his constituents as he might have been.  Second, I wanted to get the views of politicians of all hues at local, regional, national and international level, on this issue and have, or will be extending the offer of space on the blog to make their views known.

John very kindly provided the text below - I've highlighted a couple of points that have particular resonance here at WiSBAng and would like to see feedback from readers:




 The Stonehenge Traffic Action Group STAG campaign gains momentum and I would welcome the opportunity to set out my views to move forward the case for improvements to our congested local roads.

I toured the long-standing and new bottlenecks around Stonehenge with a member of Amesbury Town Council two weeks ago, met with STAG and a number of and parish council members in Shrewton on 29th September and travelled to County Hall to put the case to the most senior Highways Officer in Wiltshire.

I also raised the matter in Parliament on 10th October 2013 at Business questions.

John Glen (Salisbury) (Con):
The closure of the A344 alongside Stonehenge appears to have caused chaos along the A303. The Stonehenge traffic action group is very keen for the roads Minister to make a statement on progress made towards dualling this infamous stretch of road. Will the Leader of the House ensure that that happens?

Mr Lansley:
I completely understand my hon. Friend’s point. I sat in a queue on the A303 in August, so I had the benefit of that experience myself. I will, of course, ask my colleagues at the Department for Transport about this. As my hon. Friend and the House knows, the Department is well aware of the problem and is seeking to deal with it. I hope that, by the end of the year, it will be in a position to make announcements as a result of its study of the relevant options.

I have also secured agreement for the Minister to visit and was interviewed on Wiltshire Radio about it on 5th October and will be on Spire FM in coming days.

There are clearly immediate issues around signage near Stonehenge that the council has agreed to look into; for example,  the current roadside signs directly conflict with sat nav directions, causing a great many tourists to shuttle back and forth between Countess and Longbarrow roundabouts quite needlessly

I think that making the Stonehenge signage far clearer to give first time visitors the confidence to ignore their sat navs will make worthwhile difference and is something that can hopefully now be done fairly quickly. All possible routes to the stones need to be examined to see whether they are optimally signposted.

The bigger issue of the capacity of the A303 is another matter and does not fall under the jurisdiction of the local authority but is a national infrastructure project that is under the spotlight at the moment, with Ministers talking of capital spending once again as part of a series of upgrades to key routes around the country.

The shift from single to dual carriageways causes a great many problems along the entire length of the road and my challenge will  be to go ensure that Wiltshire’s case is heard as clearly as that of Somerset’s  representatives and ensure that any improvements cover the area around Stonehenge before they get into Somerset.

Dualling or tunnelling under the A303 past Stonehenge has been mooted before and government funding was made available before but that the project finally bit the dust after years mired in costly public enquiries and legal challenges from environmentalists, conservationists and archaeologists.

Much as I place the practical needs of the communities along the A303 first and foremost, I have to accept the political reality that the stretch of the road in my constituency runs through a UNESCO World Heritage Site and therefore any road widening here will be subject to far more international scrutiny and greater likelihood of legal challenge than almost anywhere else.

Furthermore when the costs of ameliorating these concerns are fully set out the case for justifying the expenditure when set against other deserving road improvement schemes  elsewhere in the country is an even tougher one to make.

Nevertheless, it is clear to me that our need for improved traffic flow, howsoever achieved, is every bit as urgent as other areas and I plan to make the case as strongly as I can that no money must be spent on the ‘easy’ projects further west until the Stonehenge road issue is resolved. After all, no-one can get there from the east without passing through our overstretched portion of the A303. Repetitious “feasibility” studies which wastefully go over old ground must also be avoided.

To that end, I am pleased to say that, the roads minister has agreed to meet with campaigners from this area – a meeting which I hope will help to convey the strength of locals’ concerns.

I would love to be in a position to deliver a quick and easy solution but, in all honesty, a complex debate lies ahead – one in which my personal views will compete alongside many other  concerns – some of which do not share the same assessment of what will be the best solution.

However, I can assure you it is a battle that I am very much ready for and I am engaged in.


Clearly, John has not been sitting on his laurels and has already achieved quite a bit and has more in the pipeline, or planned.

We must now make sure that the opportunity he has created for us to engage with the road minister is fully taken advantage of and that all the interest groups and Parish Councils, etc.,  from all the villages concerned, are involved in this meeting.

Friday, 11 October 2013

Yet Another Damn Feasibility Study and Another Delay!

Roads minister Robert Goodwill today announced yet another dualling feasibility study for the A303. This is expected to be complete by spring 2015 along with other key roads.

You have to ask yourself just how many feasibility studies are needed for a government of any persuasion to get the message that something needs to be done quickly.  Another long delay is completely unacceptable.
 


Methinks goodwill is going to be the last thing offered to the roads minister from this neck of the woods.   We've posted his picture so you will recognise him if you see him stuck in an A303 jam.  If you do spot him here, there or anywhere, please have a word and help him to see the error of his ways!


UPDATE:  I am sure that it is an absolute co-incidence that the next election is due to take place on Thursday 7th May 2015.  Anyone care to give odds on the reporting date for the feasibility study being Friday 8th May 2015, or later?

Monday, 7 October 2013

The High Points and Low Points of the A303

A few miles west of Andover, travellers along the A303 cross from Hampshire into Wiltshire and shortly thereafter encounter Beacon Hill; with Boscome Down and Porton Down visible to the south and Bulford over the crest of the hill to the north.

At the summit of Beacon Hill, at a height of around 560ft above sea level, is perhaps one of the most important points on the entire length of the A303.  Obviously, it's a high point because it is at the highest point of Beacon Hill. But the reason it's a low point is much less obvious.


Can you think what it might be?  Why do we regard it as a low point?  Need a clue?

OK, take a look here then:


Can you see it now?  Look in the foreground to the left of the carriageway.  Can you see how the strip of tarmac immediately to the left of the continuous white line all but disappears?   The similar strip on the right hand side of the carriageway continues for a few metres further, to roughly a point level with the back of the car transporter ahead of the Google Earth camera car.

So what?  We would argue that this point is where the A303 changes from being a high quality trunk road with carriageways wide enough to take modern traffic, to the narrow roads that lead beyond, past Stonehenge, to Winterbourne Stoke.

Apart from a few (but, not all) of the more modern dual carriageway sections and the 3-lane "death trap" sections, that little strip of tarmac never re-appears between the top of Beacon Hill and Penzance.  It never ever appears on an un-dualled section of the A303.   It represents the effective loss of 1.2 metres off the overall width of a single carriageway road, or 2.4 metres off the width of a dual carriageway.  That little strip of land, that inocuous-seeming piece of tarmac at the edge of each lane might represent the difference between life and death for a pedestrian, a cyclist or a motor-cyclist.  That's how important it is!  Life and death important.

According to the Department for Transport in its Design Manual for Roads and Bridges (2005), the specifications for rural dual and single carriageway roads are as shown below (click on the picture to get a larger view).


So East of Beacon Hill, by and large, the A303 complies with this, but West of Beacon Hill, all the way south west through Somerset and into Devon, down to the junction with the A30, it largely doesn't.  The consequences of this are fairly damning - west of Beacon Hill, the A303 is largely not fit for purpose, it certainly isn't fit to be a trunk road.  It isn't really fit to be an un-trunked A-road.  All this assumes that the lanes of the A303 (the bit between the centreline of the carriageway and the outermost edge of the edge line are 3.65 metres in width.   We should never take anything for granted and the width of these lanes is something we will return to later.

I'm sure that someone somewhere will take delight in pointing out that these are modern standards and that you can't expect an old road to match such a standard.   To an extent a fair argument, particularly for a road that had followed its current course for a century or more.  But as we saw in earlier posts, that doesn't really apply to the A303 and the stretch between Amesbury and Mere, through Winterbourne Stoke, in particular.  The A303 only came into being in 1958 - fairly recently in the great scheme of things.

Perhaps the most embarrassing point is that shown in the first photograph.  Someone, somewhere decided to make the A303 metalled surface 2.4 metres narrower to the west of Beacon Hill summit than it was to the east.   Now just which half-wit, or half-wits, were responsible for that piece of forward thinking?  Perhaps it is time to de-trunk the A303!



Saturday, 5 October 2013

Good Information is Essential to Make Our Case

One of the difficulties in pressing forward the argument for a bypass for Winterbourne Stoke and Stonehenge is that we need good information to inform our position and to rebut the arguments of the opposition.  Often, the information we need is deeply buried and seemingly inaccessible and is often under the control of the very people and organisations who are proving a stumbling block.

Part of the mission of this blog is to wheedle out that information, provide easy links to it so that you can read it for yourselves, but also to consider whether the data that is being used is valid.  Just because information comes from an official source doesn't mean it is credible, doesn't mean it makes the case that is claimed and sometimes it has been  (let's be charitable here) mis-interpreted by the opposition.  It is for you to make up your own minds whether that misinterpretation is accidental or wilful.

Links to this information will appear both in the text of related blog posts, but also under the "Favourite A303 Links" section to the right of the blog posts.   Although the blog has an easy search facility, we wanted all the useful stuff in one place to save time.



Of course, not all of the information from official sources is readily available.  However, we can make use of the Freedom of Information Act (FOIA) to try and get at much of that.  It is very easy to do and essentially means you just write to the official body you think controls the information and ask them for it.  In simple terms, if the information you have asked for is not exempt from the FOIA (eg it's a national security issue), it isn't going to cost too much and take too long to answer it (disproportionate cost to the public interest value) and isn't covered by any other statutory "get out" clauses, then the information owner is legally obliged to provide the answer within a very short space of time.  If they don't, the whole issue can be escalated to the Information Commissioner for review.  The good news is that much of the information these days is held in searchable, electronic databases (and more historical data is digitised daily), so rejecting an FOIA on the grounds of cost is becoming increasingly indefensible.  The best FOIA questions are those where you may already know, or strongly suspect, what the answer is, but want original documents or hard facts and figures to reference in making your case. 



The whole FOIA process is made so much easier if you use the What Do They Know? website.   This is a smashing resource that gives you advice on how best to formulate an FOIA request, sends it off to the appropriate authority on your behalf, tracks progress and warns you if the recipient is failing to respond in time.  It provides an easy way of commenting on a response and then asking supplementary questions.  However, the biggest advantage is that the whole process is public.  If you make an FOIA request on your own, only you get the answer, it isn't public, isn't searchable and so isn't as useful to others.

In a campaign like this one, getting the information into the public domain is vital; so if you are tempted to make an FOIA request, please use What Do They Know.

So, what information is there already.  Well, there are already links to the Trunk Road Act (1936) and the later amendment to it, the Trunk Road Act (1946).   All good historical scene setting on trunk roads.  If you like the minutiae of Acts of Parliament, they may be of interest to you.



There are two excellent recent documents that everyone involved in this campaign should read and refer to.  The first is "The Eddington Transport Study" of December 2006 - written for the British Government by the Australian former CEO of BA, Sir Rod Eddington

The Eddington Transport Study set out the case for action to improve road and rail networks, as a "crucial enabler of sustained productivity and competitiveness". The report's main conclusions were that Britain has transport networks that provide the right connections, in the right places, to support the journeys that matter to economic performance. But roads in particular were in serious danger of becoming so congested, the economy would suffer.  Something most of us would agree with.



The second document, and by far and away the single most important information source we have come across, so far, is the "A303, A358, A30: Corridor Improvement Programme - Economic Impact Study" of October 2012.  This most boring sounding report was produced by Parsons Brinckerhoff for Somerset County Council.   What on earth has a report commissioned for Somerset County Council got to do with the little village of Winterbourne Stoke in Wiltshire, rat-running on the roads around and the problems at Stonehenge?

Well you might ask.  Somerset Council are to be congratulated for an inspired piece of work. Parsons Brinckerhoff undertook an appraisal of the economic benefits of dualling the full length of the A303 between Amesbury and Honiton as well as the A358 between Ilminster and Taunton.  The bottom line, for all of us, is that if the A303 and the A3588 were both dualled, then in the context of this plan as a whole, for every pound spent on providing an A303 by-pass for our village of Winterbourne Stoke, the economy would recover £1.80.  For every pound spent putting the A303 in a tunnel the economy would recover £1.80.   The economic advantage is astonishing.  Isn't it a crying shame that Wiltshire Council hadn't either participated fully with Somerset Council and produced a joint document with breakdowns to county level or commissioned a purely Wiltshire-centric study at any point over the last 30 years?

Despite the horrific title, this report is a really good read - and we suggest everyone does at least dip into it. It is full of useful facts and figures that we can make use of in the campaigns to improve our lot.   It is also very well researched and the authors have, in places demonstrated they have seen through the inadequacies of some of the Government's own data processing and interpretation.  Perhaps the best example of this is when it comes to traffic volumes.

Consider the traffic statistics for our village of Winterbourne Stoke.  They look fairly interesting, but one set of numbers got me thinking - those for bicycles.  It seems that four times more bikes go west through our village than go east.  There could be lots of reasons for this, but amongst the most likely reasons is the fact that it may simply be an aretfact of the way data was collected.   Thankfully, the Department of Transport has published its methodology for Road Traffic Estimates.

More turgid stuff, but what it appears to say is that they try to do a manual count on each sampled road length, like the census point 6874 on the A303 at Winterbourne Stoke, as often as they can.  In reality, this means that every 1, 2, 4 or 8 years (depends on the road), they conduct a manual survey for 12 hours.  Of course, they don't work weekends, public holidays or school holidays; nor do they survey between November and February.  They only undertake manual counts on the 110 what they call 'neutral days' each year.  I guess that is DoT speak for saying they only work on Tuesdays, Wednesdays and Thursdays when it isn't cold - poor dears!

These infrequent manual counts are supplemented by electronic input from a national network of 180 (yes, you read that correctly 180) of Automatic Traffic Counters that are used to produce what they call "expansion factors" to interpolate the traffic flow 24 hours a day, 365 days a year; something DoT refer to as the annual average daily flow (AADF).  In other words, this is pseudo-science, a wise-arse guess, or more succinctly, in the vernacular, complete and utter bollocks.

Interpolating from data derived in this way has a number of effects.  Regardless of any seasonal road traffic variations, the inbuilt methodological bias will overestimate the AADF on urban roads where traffic flow is predominantly on weekdays and underestimate traffic flow on rural roads.  The methodology will grossly underestimate traffic flow on the A303 and similar rural trunk routes to holiday destinations, where high traffic flows are predominantly over the weekend, bank holiday and school holiday periods when the manual data is simply not collected.

Worse is to come.  Investment in roads inevitably follows the perceived usage 'statistics'.  When the  usage statistics are as flawed or fictitious as the AADF, the money will be used for urban roads and not rural ones.  It's all down to perception management - we have to ensure the debate questions and asks for validation of every bit of data that is presented - regardless of the source.



Parsons Brinckerhoff, in undertaking the "A303, A358, A30: Corridor Improvement Programme - Economic Impact Study" appear to have looked at the DoT methodology and found it wanting.  They seem to have come up with a different, possibly more robust approach to traffic flow (see section 2.2 of the above report), but it is still based on the manual and automated traffic counts.  We'll be doing some more digging to see just how robust this approach really is.

We suspect that the report may still underestimate traffic flows on the A303, but the good news to end this post on, is simply this. Parsons Brinckerhoff may also have have underestimated the financial benefit to cost ratio of dualling the A303 and thus providing a bypass to Winterbourne Stoke.  That is even without considering both the financial and non-financial benefits to Shrewton, Orcheston, Tilshead, Larkhill, Durrington, Berwick St James, Stapleford and all the other local villages currently suffering